Client/Executive Agency:
Road Transport & Highways Division, Bangladesh

Main Contractor for Package CP-03 & 04:
Italian-Thai Development Public Co. Ltd.

ITD LOGO

Contracts Awarded to DCDL under Package CP-03 & 04

Sl. No. Contract Ref. No. Description of Work Date of Award Date of Completion
A) Temporary Works at Birulia Casting Yard
01 J2354-WO-1707-0020, 0063, 0086, 0085, 0084, 0116, 0115, 0112, 0141, 0161 Thai Camp Construction Work, General Camp Construction Work, Crane Foundation (10T and 70T), Access Road (RCC), Guard House (Steel Work), Second General Camp, U-Drain, Boundary Wall, Substation Works, Canteen Construction Jul 2017 Jun 2018
B) Temporary Works at Agargaon Site
02 J2354-WO- 118080662, 118120009, 118100314, 118100399, 119010358, 118080383, 118110428, 118120008, 119010348, 119010347, 596, 1037, 1173 ITD New Office, ITD New Toilet, ITD Canteen Extension, Old Office Renovation, Driver and Store Room, PWD Area Ansar Camp Extension, PP8 Toilet Work, NKDM Area Walkway Feb 2018 Feb 2019
C) Main Line Works: Pile Cap, Pier and Pier Head
03 J23554/SC/ 1806/0024 Pile Cap, Pier and Pier Head Works, Station Works at Mirpur-11, Station Works at Kazipara, Balanced Cantilever at P-123 and P-247, Seismic Buffer and Bearing Base Work Jun 2018 Nov 2019
04 J2354/SC/ 1811/0064 Portal Pier Work for P-32, 33, 34, 35, 36, 172 Nov 2018 Oct 2019
05 J2354/SC/ 1811/0064 Portal Pier Works P-352, 353, 354, 355, 369, PN-373 Nov 2018 Ongoing
06 J23554/SC/ 1911/0125 Pier Table Work at CP-04 (P-247, 248) Nov 2018 Ongoing
07 J23554/SC/ 1911/0127 Deck Slab Work at CP-03 Nov 2019 Jan 2020
* The Main Contractor has split the work into smaller packages. As such, more work orders are expected to be received until the completion of the project.

Main Contractor for Package CP-05:
Tekken - Abdul Monem Ltd - Abenikko Joint Venture

TAA Logo 2

 

Contracts Awarded to DCDL under Package CP- 05

Sl. No. Contract Ref. No. Description of Work Date of Award Date of Completion
Main Line Works: Pile Cap, Pier and Pier Head
01 PO-19-00462 Construction of Pier and Pier Head for 20 Nos. Piers Aug 2019 Ongoing
* The Main Contractor has split the work into smaller packages. As such, more work orders are expected to be received until the completion of the project.

Main Contractor for Package CP-06:
Sumitomo Mitsui Construction Company Ltd - ITD Joint Venture

SMCC-ITD JV

Contracts Awarded to DCDL under Package CP- 06

Sl. No. Contract Ref. No. Description of Work Date of Award Date of Completion
A) Temporary Works at Gabtoli Casting Yard
01 WO-55, 59, 67, 93, 121, 141 Boundary Wall, Casting Yard Main Road, Engineers' & Staff Accommodation, Canteen Construction, U-Ditch, Truck Scale Road, Water Network, RO Plant Oct 2018 Mar 2019
B) Temporary Works at TSC Batching Plant
02 WO-87, 319050030, 319050033 Road and Sewage Line (BP), Internal Road Work, Drainage Work, Main Gate Work Nov 2018 Mar 2019
C) Main Line Works: Pile Cap, Pier and Pier Head
03 WO No. 319050041 Pile Cap Work for 10 Nos. Piers May 2019 Ongoing
04 WO No. 319100016 Pile Cap Work for 10 Nos. Piers Oct 2019 Ongoing
05 WO No. 31911002 Pile Cap Works for Balance Cantilever Pier Nov 2019 Ongoing
06 WO No. 31906003 Construction of Pier and Pier Head for 10 Nos. Piers May 2019 Ongoing
07 WO No. 319100015 Construction of Pier and Pier Head for 10 Nos. Piers Oct 2019 Ongoing
08 WO No. 319110022 Construction of Pier and Pier Head for 10 Nos. Piers Nov 2019 Ongoing
* The Main Contractor has split the work into smaller packages. As such, more work orders are expected to be received until the completion of the project.

PROJECT PROFILE

The MRT Line-6 is an elevated Metro Rail system to be implemented in Dhaka, under a fast track priority initiative of the Government of Bangladesh. Once implemented, the MRT Line-6 will run from Uttara to Motijheel, covering 18.9 km with 16 stations along the way. The project is jointly financed by the Government of Bangladesh and Japan International Cooperation Agency (JICA). Once finished, it will be the most time efficient, reliable, safe, comfortable and environment friendly solution, that will transform Dhaka into a more active, commutable and sustainable city.

ROUTE MAP OF MRT LINE-6

 ROUTE MAP OF MRT LINE-6 - Copy