OUR COMPLETED PROJECTS
KARNAPHULI WATER SUPPLY PROJECT (P2/W2): PIPELINE INSTALLATION
Client/Executive Agency: | Chattogram Water Supply & Sewerage Authority (CWASA) |
Main Contractor: | Kubota-Kolon Global Joint Venture |
Contracts Awarded to DCDL
Sl. No. | Contract Ref. No. | Description of Work | Date of Award | Date of Completion |
01 | W2P-016 | Pipe laying (Conveyance) | Oct 2016 | Jun 2018 |
02 | W2P-017 | Sand Supply | Oct 2016 | Jun 2018 |
03 | W2P-018 | Pipe laying (TR1 CUET) | Oct 2016 | Jun 2018 |
04 | W2P-019 | Sand Supply (TR1) | Oct 2016 | Jun 2018 |
05 | W2P-020 | Pipe laying (Baized Bostami Road) | Oct 2016 | Jun 2018 |
06 | W2P-021 | Trail Hole | Oct 2016 | Jun 2018 |
07 | W2P-048 | Pipe laying Work | May 2017 | Aug 2018 |
08 | W2P-051 | Pipe laying | Jul 2017 | Oct 2018 |
09 | W2P-055 | Pipe laying Work | Sep 2017 | Nov 2018 |
PROJECT PROFILE Installation of pipelines was part of the second package (Package W-2) of Karnaphuli Water Supply Project Phase-2. The main activities of the project consisted of setting up a water treatment plant with a capacity of 143 million litres per day, constructing one water intake plant, installing 38 kilometres of transmission pipeline and 505 kilometres of distribution pipeline. Chattogram WASA has undertaken this project to ensure uninterrupted supply of purified water from the Karnaphuli river and to provide safe water to the inhabitants of Chattogram, which will cost around Tk 44.91 billion. |