OUR COMPLETED PROJECTS

KARNAPHULI WATER SUPPLY PROJECT (P2/W2): PIPELINE INSTALLATION

Client/Executive Agency: Chattogram Water Supply & Sewerage Authority (CWASA)
Main Contractor: Kubota-Kolon Global Joint Venture
Kubota Kolon JV

Contracts Awarded to DCDL

Sl. No. Contract Ref. No. Description of Work Date of Award Date of Completion
01 W2P-016 Pipe laying (Conveyance) Oct 2016 Jun 2018
02 W2P-017 Sand Supply Oct 2016 Jun 2018
03 W2P-018 Pipe laying (TR1 CUET) Oct 2016 Jun 2018
04 W2P-019 Sand Supply (TR1) Oct 2016 Jun 2018
05 W2P-020 Pipe laying (Baized Bostami Road) Oct 2016 Jun 2018
06 W2P-021 Trail Hole Oct 2016 Jun 2018
07 W2P-048 Pipe laying Work May 2017 Aug 2018
08 W2P-051 Pipe laying Jul 2017 Oct 2018
09 W2P-055 Pipe laying Work Sep 2017 Nov 2018

PROJECT PROFILE

Installation of pipelines was part of the second package (Package W-2) of Karnaphuli Water Supply Project Phase-2. The main activities of the project consisted of setting up a water treatment plant with a capacity of 143 million litres per day, constructing one water intake plant, installing 38 kilometres of transmission pipeline and 505 kilometres of distribution pipeline. Chattogram WASA has undertaken this project to ensure uninterrupted supply of purified water from the Karnaphuli river and to provide safe water to the inhabitants of Chattogram, which will cost around Tk 44.91 billion.