OUR ONGOING PROJECTS

FIRST DHAKA ELEVATED EXPRESSWAY PROJECT

Client/Executive Agency: Bangladesh Bridge Authority
Main Contractor: Italian-Thai Development Public Co. Ltd.
ITD LOGO

Contracts Awarded to DCDL

Sl. No. Contract Ref. No. Description of Work Date of Award Date of Completion
01 WO-0002 Site Office Construction Apr 2014 Sep 2014
02 WO-0007 Electrical Work at Site Office Building Apr 2014 Oct 2014
03 WO-0008 Wash Room Construction Work Jul 2014 Sep 2014
04 FDEE-DCDL-002 Batching Plant Jan 2015 Mar 2015
05 FDEE-DCDL-1508-018 Sand Filling & Access Road Aug 2015 Aug 2015
06 FDEE-DCDL-1510-025 Fencing Work Oct 2015 Nov 2015
07 FDEE-DCDL-1510-035 Staff Accommodation Dec 2015 Feb 2016
08 FDEE-DCDL-1604-067 Construction of Reinforced Concrete Pile Cap Apr 2016 Dec 16
09 FDEE-DCDL-1608-088 Construction of Water Drainage System and Manhole at FDEE's Precast Yard Aug 2016 Dec 16
10 FDEE-DCDL-1701-107 Construction of Reinforced Concrete Pile Cap – Lot 2 Jan 2017 Mar 17
11 FDEE-DCDL-1710-152 Construction of Reinforced Concrete Pile Cap – Lot 3 Oct 2017 Dec 2017
12 FDEE-DCDL-1711-165 Road Restoration after Column Work at Pier 79, 82, 83 and 103 Nov 2017 Ongoing
* The Main Contractor has split the work into smaller packages. As such, more work orders are expected to be received until the completion of the project. * The Main Contractor has split the work into smaller packages. As such, many more work orders are expected to be received until the completion of the project. * The Main Contractor has split the work into smaller packages. As such, many more work orders are expected to be received until the completion of the project. * The Main Contractor has split the work into smaller packages. As such, many more work orders are expected to be received until the completion of the project. * The Main Contractor has split the work into smaller packages. As such, many more work orders are expected to be received until the completion of the project.

PROJECT PROFILE

The First Dhaka Elevated Expressway (FDEE) is Bangladesh's first elevated expressway project, which will connect the Shahjalal International Airport with Kutubkhali (Dhaka-Chattogram Highway) via Mohakhali, Tejgaon and Kamalapur, alongside the existing rail track. It is one of the largest infrastructure projects taken up by the incumbent government to ease traffic congestion in the capital. It will be 46.73km long including the connecting roads and will cost around Tk 122 billion. The project is funded under Public Private Partnership (PPP) with a condition of 25 years concession period to collect toll after completion.